Several major street projects have reached significant construction milestones this summer as work continues on more than $76 million in street, bridge and waterline improvements across Tulsa.
From North Tulsa to South Tulsa, crews are reconstructing streets, replacing aging waterlines, rehabilitating bridges and expanding critical transportation corridors as the largest streets project in Tulsa’s history – carried out primarily through Improve Our Tulsa – continues.
As construction continues, motorists may experience temporary lane closures, traffic shifts and detours in some areas. The City encourages drivers to plan ahead, follow posted traffic control, and use caution when traveling through active work zones.
The following projects are currently under construction or scheduled to begin soon:
-
Harvard, 21st to 31st – This street widening project is halfway complete, with two-way traffic currently being diverted to the east side of Harvard. The City of Tulsa has contracted with Crossland Heavy Contractors for this $2.7 million project funded through the Improve our Tulsa 2 sales tax extension. Construction is scheduled for completion in early 2027.
-
Gilcrease Museum Road, Admiral to Pine – This street reconstruction project is 65% complete, with Gilcrease Museum Road currently closed from West Edison Street to West Pine Street. The City of Tulsa has contracted with Becco Contractors for this $25 million project funded through the Improve Our Tulsa 2 sales tax extension. Construction is scheduled for completion in late 2026.
-
91st, Memorial to Mingo – This street widening project is 80% complete, with two-way traffic currently being diverted to the east side of 91st. The City of Tulsa has contracted with Tri-Star LLC for this $12.8 million project funded through the Improve Our Tulsa 2 sales tax extension. Construction is scheduled for completion in early 2027.
-
Utica, Admiral to Pine – This street rehabilitation and waterline replacement project is almost halfway complete, with traffic currently reduced to one lane on the east side of Utica. The City of Tulsa has contracted with Becco Contractors for this $15,137,000 Improve Our Tulsa project. Construction is scheduled for completion in summer of 2027, weather permitting.
-
91st, Harvard to Yale – This street rehabilitation and waterline reconstruction project is partially complete, with 91st Street closed just east of Harvard. The City of Tulsa has contracted with Paragon Contractors for this $4,985,000 Improve our Tulsa 2 project. Construction is scheduled for completion this fall, weather permitting. The road is expected to be reopened to two-way traffic ahead of the upcoming school year, with a full construction timeline to be finalized and communicated to residents by the middle of next week.
-
15th, Lewis to Harvard – This street rehabilitation project has just begun, with two-way traffic currently being diverted to the North side of 15th. The City of Tulsa has contracted with Becco Contractors for this $3,421,000 Improve Our Tulsa project. Construction is scheduled for completion in summer of 2027, weather permitting.
-
Utica, 11th to 15th – This street rehabilitation is partially complete, with two-way traffic currently in place along Utica. The City has contracted with Becco Contractors for this $4,987,000 Improve our Tulsa project. Construction is scheduled for completion in early 2027, weather permitting.
-
Detroit, 4th to Lansing – This street rehabilitation and waterline replacement project has just recently begun, with traffic currently being diverted to the north side of Detroit. As part of the project, portions of 4th Street along Detroit Avenue will be permanently converted to two-way traffic, aligning with recommendations from PlaniTulsa, the City’s comprehensive development plan, which identified downtown streets as being better suited for two-way operations. The City of Tulsa has contracted with Tri-Star Construction for this $3,197,000 Improve out Tulsa project. Construction is scheduled for completion in spring of 2027, weather permitting.
-
Pine, Mingo to Garnett – A street and bridge rehabilitation project is expected to begin next month on East Pine Street, from South Mingo Road to North Garnett Road. The City has contracted with Paradigm Construction and Engineering for this $2.6 million Improve our Tulsa project. Construction is scheduled for completion in spring of 2027, weather permitting. More information will be made available soon.
-
31st, Yale to Sheridan – A street and bridge rehabilitation project will begin next month on East 31st Street, from South Yale Avenue to South Sheridan Avenue. The City has contracted with Becco Contractors for this $2 million Improve our Tulsa project. Construction is scheduled for completion in spring of 2027, weather permitting. More information will be made available soon.
The City will continue providing project updates as construction progresses and appreciates the public’s patience while these long-term infrastructure improvements are completed.